Project Timeline

General Timeline

  • July – August 2018: Complete Design Development Phase
  • August – October 2018:  Final Construction drawings
  • November – December 2018: Bid out Project
  • December 2018- January 2019: Owners move out
  • January 2019-February 2019: Start Construction

Building & Activity Dates

AC Clark Library 1st Floor (Map Library)

Owner Move Out January 1 ‐ January 31 (2019)
Construction February 4 ‐ End of March (2019)

Bangsberg Offices & 3rd Floor

Owner Move Out January 1 ‐ January 31 (2019)
Construction February 4 ‐ End of May 3 (2019)

Sattgast 2nd & 3rd Floor

Owner Move Out January 1 ‐ January 31 (2019)
Construction February 4 ‐ End of May (2019)

Bensen Hall 3rd and 4th Floor

Owner Move Out January 1 ‐ January 31 (2019)
Construction February 4 ‐ End of June (2019)

Sattgast 1st Floor

Owner Move Out May 13 ‐ May 17 (2019)
Construction May 13 ‐ End of June (2019)

AC Clark Library 2nd & 3rd Floors

Owner Move Out May 13 ‐ May 24 (2019)
Construction May 27 ‐ August (2019)

Hagg Sauer

Owner Move Out May 13 ‐ May 17 (2019)
Abatement
May 27 ‐ June 22 (2019)
Demolition
June 25 2019 ‐ August 30, 2019
Construction September 1, 2019 – TBA

Bangsberg Remaining

Owner Move Out May of 2020
Construction June 2020 ‐ August 2020